Best Life Projects
 

The construction of the 4 pilot projects has been completed, and they have been open to the public since May 2014.
As regards the procedure of the Strategic Environmental Assessment (SEA), the Environmental Report of the Environmental Regeneration Programme of the Pontine Plain has been completed.
The lessons in the schools of the Pontine Plain, and the guided tours for students at the pilot installation in the National Park of Circeo, have already taken place.
The final publication has been completed and distributed during the final project conference.

06.05.2015

Report of the environmental monitoring


The report of the environmental monitoring of the pilot projects of Rewetland is now available. The condition of the water, flora and fauna has been monitored through campaigns which took place from June 2013 to May 2014, analyzing chemical, hydro-morphological and biological parameters. The results of the operational phase of the pilot projects will be available with the next environmental report which will be ready from June 2015.

Download the summary of the report of the environmental monitoring


24.04.2015

Final Report of the project Life+ Rewetland


The document, developed by the Rewetland partnership, is divided into the following sections: an introduction to the faced problems and the implemented solutions; an administrative section, which explains the structure and the management of the project; a technical section, which describes in detail the obtained results.

Download the Final Report

01.07.2014

Layman's report


Please download here the Layman's report, a non-technical summary outlining the background of the project, and the objectives and outcomes that have been achieved.

Download layman's report


12.06.2014

Rewetland final publication


It is possible to download the Rewetland final publication that, in addition to a comprehensive description of the state of the Pontine plain, illustrates objectives and results obtained with the implementation of the project.

Download final publication
Download English text

(Final version of fully formatted publication in English will be available soon)


26.07.2013

Approval of the Preliminary Strategic Document of the Program for Environmental Rehabilitation of Agro Pontino


The Preliminary Strategic Document of the Program for Environmental Rehabilitation of Agro Pontino was officially approved by the Provincial Council by resolution no. 16 of 26 July 2013. It constitutes now the basic tool that will guide all future interventions of constructed wetlands that will be built in the province of Latina.

In attachment the resolution,  the Preliminary Strategic Document, the Italian and English abstract.


28.01.2013 Action 8.2 - summary

Guidelines for actions on drainage canals.
Consortium for the Land Reclamation of the Agro Pontino.

download summary


Action 8.1 - summary

Action Plan - Final report about objectives-scenarios.
Province of Latina.

download summary


Action 7.4 - summary

SWOT analysis and matrix of pressure factors.
Province of Latina.

download summary


Action 7.2 - summary

Analysis on the Hydrographical network in the Consortium area.
Consortium for the Land Reclamation of the Agro Pontino.

download summary


Action 6.4 - summary

Geodatabase of the CBAP.
Consortium for the Land Reclamation of the Agro Pontino.

download summary


13.06.2011 Action 5.3 - summary

Feasibility Study for the Pilot Plan 3.
Consortium for the Land Reclamation of the Agro Pontino.

download summary


Action 5.2 - summary

Feasibility Study for the Pilot Plan 2.
Municipality of Latina.

download summary


Action 5.1 - summary

Feasibility Study for the Pilot Plan 1.
Province of Latina,
Circeo National Park.

download summary (italian version)

28.03.2011 Action 4.5 - summary

Report on the enviromental status of the "Pontine Plane"..
U-Space s.r.l..

download summary


Action 4.4 - summary

Regulatory Framework.
U-Space s.r.l..

download summary


Action 4.3 - summary

Report on the water quality in the "Pianura Pontina".
Province of Latina.

download summary


Action 4.2 - summary

Relazione sullo stato delle zone umide costiere.
Circeo National Park.

download summary


Action 4.1 - summary

Report on the use of water resources for agriculture.
Consortium for the Land Reclamation of the Agro Pontino.

download summary